St Silas Estate Boiler Installations Project
Overview
This page has been designed to provide information about the heating project for residents of the St Silas estate.
Part of the estate will be taken off the communal heating system, and have individual combi-boilers installed. The remaining properties will stay on a refurbished communal system.
Please see below for a list of blocks, and which sort of heating system they will receive.
Installation of new individual boilers:
- Halstow
- Lenham
- Wingham
- Westwell
- Stonegate
Renewal of the communal heating system:
- Southfleet
- Headcorn
- Cheriton
- Chislet
- Leysdown
- Fordcombe
- Burmarsh
Why your views matter
This page will be updated with regular information about the project. Please scroll to the bottom of the page to see the latest events which will be held about the project.
Get in touch
We would like to hear your opinions about this page, please get in touch with us if you have any ideas on content you would like to see published here.
Email: andrew.georgiou@camden.gov.uk
Events
-
Meet the Contractor Meeting - Phase 2
From 23 Jan 2020 at 18:30 to 23 Jan 2020 at 20:00We are now able to invite you to meet some of the staff from the company who will carry out the work, Invicta Building Services. These will be key staff who will be on site during the works. We have also invited the Resident Liaison Officer (RLO), who will visit each resident and will be your first point of contact from the contractor. There will also be staff from Camden Council available to talk to you about the project. This meeting will cover the following blocks:
• Southfleet
• Headcorn
• Cheriton
• Chislet
• Leysdown
• Fordcombe
• Burmarsh
We can give you information about:
• Work to your home
• How the work will be carried out safely
• How the work will be organised
• How we will keep you informed as work progresses